Project Overview
This solar setup comprises two plants with capacities of 420 kW and 220 kW, each equipped with 110kTL TBEA inverters. The system is connected to a single grid and supported by one generator. A unique aspect of these plants is that the inverters and ATS panels are installed at different locations, and the setup includes two bus-bars to manage power distribution efficiently. This configuration ensures reliable operation, optimal energy management, and smooth coordination between solar generation, the grid, and the generator.
Key Highlights
- TBEA 110KTL Inverters and having Two bus bars
Project Details
- Client
- MK Engineers & Constructors Pvt. Ltd
- Sector
- Government
- System Type
- Automation
- Capacity
- 920 KWp
- Location
- Lahore, PUNJAB
- Commissioned
- March 2024