Project Overview

This site comprises two plants: a 1 MW first phase and a 900 kW second phase, supported by 4–5 generators. All inverter stations across the site use Huawei inverters of varying capacities—115kTL, 150kTL, and 50KTL—installed at different locations. Both plants are connected to HT grids, with HT meters installed to monitor grid import and export. An advanced monitoring platform ensures real-time supervision, energy optimization, and controlled export and import across the entire site.

Key Highlights
  • Integrated a generator into the system to optimize fuel consumption and improve overall energy efficiency
  • Controlling import and export to the grid
Project Details
Client
Beacon Energy